Escalation Factors for Middle Fork Snoqualmie River Road

Project Number: WA PFH 29-1(1)
Project Name: Middle Fork Snoqualmie River Road
Bid Opening Date: February 21, 2014

Base Price Indexes

Asphalt Cement

Asphalt Weekly Location: Seattle, Washington

Week / DateAsphalt  ($/US ton)
1 / January 27, 2014505.00
2 / February 3, 2014505.00
3 / February 10, 2014505.00
4 / February 17, 2014505.00
Base Price Index505.00

 

Computation Approaches Used to Determine Base Price Indexes

Asphalt Cement Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.