HI STP SR50(1) HANAPEPE RIVER BRIDGE

Project Overview

The Central Federal Lands Highway Division of the Federal Highway Administration, in cooperation with the Hawaii Department of Transportation is developing a project located on the Kaumualii Highway, Route 50, at M.P. 16.57, the Hanapepe River Bridge, on the Island of Kauai.

A Final Environmental Assessment (EA) and Finding of No Significant Impact (FONSI) has been prepared pursuant to HRS Chapter 343 (as amended), and Hawaii Administrative Rules Title 11, Chapter 200.   The document is available for download and review by clicking on the All Documents link on the left side of this page.

Project Details:

In Development
Island of Kauai, HI

The proposed project is located on the Kaumualii Highway (Route 50), the coastal perimeter road serving the west side. The subject bridge crosses the Hanapepe River near Hanapepe Bay. The project would improve the safety and reliability of the Hanapepe Bridge, through rehabilitation or replacement, addressing bridge width, load capacity, bridge railing and transitions, bridge approaches and to mitigate the effects of scour.


Update 6/1/2018

Temporary By-pass Bridge: The temporary bridge and bridge deck have been placed. The contractor is preparing the site for the permanent bridge contractor to begin work.

Permanent Bridge: The permanent bridge construction contract was awarded to WW Clyde Construction on APRIL 13, 2018. The construction Notice to Proceed is targeted for issuance in June/July 2018 following completion of the temporary bridge.


Update 5/1/2018

Temporary By-pass Bridge: The bridge piers have been constructed and the temporary bridge is scheduled to be launched into place in early May.

Permanent Bridge: The permanent bridge construction contract was awarded to Hawaiian Dredging on APRIL 13, 2018 TO WW Clyde Construction. The construction Notice to Proceed is targeted for issuance in June 2018 following completion of the temporary bridge.


Update 4/1/2018:

Construction: There is no new information to share at this time.


Update 3/1/2018

Construction: Funding has been identified for construction of the permanent Hanapepe River Bridge.

A MATOC contract has been awarded to support construction of this project. The project is currently being bid amongst MATOC contract holders, with award anticipated in April 2018. A Notice to Proceed will be dependent on completion of the temporary bridge project, described below, targeted for May 2018.

The temporary by-pass bridge project was awarded to Hawaiian Dredging on June 1, 2017. The temporary by-pass bridge will be constructed to provide traffic access during construction of the permanent bridge. Ongoing construction activities include construction of the roadway approaches to support driving pipe pile to establish the temporary bridge foundation. Once the foundation has been completed, an ACROW bridge will be assembled as the future bypass for public traffic during construction of the permanent bridge. The temporary bridge will be removed and the site will be restored to precondition upon completion of the permanent bridge project. The temporary bridge project is anticipated to be completed in April 2018.


Update 2/1/2018

Construction: Funding has been identified for construction of the permanent Hanapepe River bridge. A MATOC contract has been awarded to support construction of this project. The project is currently being bid amongst MATOC contract holders, with award anticipated in February 2018. A notice to proceed will be dependent on completion of the temporary bridge project, described below, targeted for March 2018.

The temporary by-pass bridge project was awarded to Hawaiian Dredging on June 1, 2017. The temporary by-pass bridge will be constructed to provide traffic access during construction of the permanent bridge. Ongoing construction activities include construction of the roadway approaches to support driving pipe pile to establish the temporary bridge foundation. Once the foundation has been completed, an ACROW bridge will be assembled to as the future bypass for public traffic during construction of the permanent bridge. The temporary bridge will be removed and the site will be restored to precondition upon completion of the permanent bridge project. The temporary bridge project is anticipated to be completed in late February 2018.


Comments
Construction Amount Between $10,000,000 and $25,000,000

Sections

Map showing general vicinity of project
View a larger interactive map of the project area.

Project Details
Project # HI STP SR50(1)
Project Name HANAPEPE RIVER BRIDGE
Location Island of Kauai
Status In Development

Contact Information

Project Manager: Mike Will
Phone: 720-963-3647
Email: michael.will@dot.gov

Federal Highway Administration
Central Federal Lands Highway Division
12300 West Dakota Avenue
Lakewood, CO 80228
720-963-3500