HI STP SR50(1) HANAPEPE RIVER BRIDGE

Project Overview

The Central Federal Lands Highway Division of the Federal Highway Administration, in cooperation with the Hawaii Department of Transportation is developing a project located on the Kaumualii Highway, Route 50, at M.P. 16.57, the Hanapepe River Bridge, on the Island of Kauai.

A Final Environmental Assessment (EA) and Finding of No Significant Impact (FONSI) has been prepared pursuant to HRS Chapter 343 (as amended), and Hawaii Administrative Rules Title 11, Chapter 200.   The document is available for download and review by clicking on the All Documents link on the left side of this page.

Project Details:

Under Construction
Island of Kauai, HI

The project is located on the Kaumualii Highway (Route 50), the coastal perimeter road serving the west side. The subject bridge crosses the Hanapepe River near Hanapepe Bay. The project improves the safety and reliability of the Hanapepe Bridge, through rehabilitation or replacement, addressing bridge width, load capacity, bridge railing and transitions, bridge approaches and to mitigate the effects of scour.


Update 12/1/2018

There is no new information to share at this time.


Update 11/1/18

Temporary By-pass Bridge: The temporary bridge and bridge deck have been placed. Work on the temporary bridge is considered complete. Project closeout procedures are currently underway. Construction of the temporary bridge roadway approaches will be completed by the contractor working on the permanent bridge construction.

Permanent Bridge: The permanent bridge construction contract was awarded to WW Clyde on April 13, 2018. The construction NTP was issued on August 6, 2018. The contract duration is 684 Calendar days which will establish a contract completion date of June 20, 2020. A project blessing occurred on Monday October 1, 2018 for more information on the blessing see: http://hidot.hawaii.gov/administration/blessing-ceremony-held-for-hanapepe-river-bridge-replacement-project/ The contractor has begun mobilization to the project site and is currently working through submittals prior to initiating substantial on-site work. Initial project work includes preparation of the temporary utility relocations and construction of the roadway approaches to the by-pass bridge (targeted to be in place prior to early calendar year 2019).


Update 10/1/2018

Temporary By-pass Bridge: The temporary bridge and bridge deck have been placed. Work on the temporary bridge is considered complete. Project closeout procedures are currently underway. Construction of the temporary bridge roadway approaches will be completed by the contractor working on the permanent bridge construction.

Permanent Bridge: The permanent bridge construction contract was awarded to WW Clyde on April 13, 2018. The construction NTP was issued on August 6, 2018. The contract duration is 684 Calendar days which will establish a contract completion date of June 20, 2020. Following a project blessing scheduled for early October, contractor operations will include mobilization of equipment to the project site.


Update 9/1/2018

Temporary By-pass Bridge: The temporary bridge and bridge deck have been placed. Work on the temporary bridge is considered complete. Project closeout procedures are currently underway.

Permanent Bridge: The permanent bridge construction contract was awarded to WW Clyde on April 13, 2018. The construction NTP was issued on August 6, 2018. The contract duration is 684 Calendar days which will establish a contract completion date of June 20, 2020. Contractor operations expected during September/October include mobilizing equipment to the project site.


Update 8/1/2018

Temporary By-pass Bridge: The temporary bridge and bridge deck have been placed. Work on the temporary bridge is considered complete and the contractor, Hawaiian Dredging, has initiated demobilization of the project site to allow for the permanent bridge contractor (WW Clyde) to begin work.

Permanent Bridge: The permanent bridge construction contract was awarded to WW Clyde on April 13, 2018 2018 for $35,188,420.00. The construction Notice to Proceed is targeted for issuance in August 6, 2018. The contract duration is 684 Calendar days which will establish a contract completion date of June 20, 2020. Contractor operations expected during August and September include mobilizing equipment to the project site.


Update 7/1/2018

Temporary By-pass Bridge: The temporary bridge and bridge deck have been placed. Work on the temporary bridge is considered complete and the contractor, Hawaiian Dredging, is preparing the site for the permanent bridge contractor (WW Clyde) to begin work.

Permanent Bridge: The permanent bridge construction contract was awarded to WW Clyde on April 13, 2018. The construction NTP is targeted for issuance in July 2018 where the contractor will begin mobilization to the project site.


Comments
Construction Amount $35,188,420.00

Sections

Map showing general vicinity of project
View a larger interactive map of the project area.

Project Details
Project # HI STP SR50(1)
Project Name HANAPEPE RIVER BRIDGE
Location Island of Kauai
Status Under Construction

Contact Information

Project Manager: Mike Will
Phone: 720-963-3647
Email: michael.will@dot.gov

Federal Highway Administration
Central Federal Lands Highway Division
12300 West Dakota Avenue
Lakewood, CO 80228
720-963-3500