HI STP SR83(2) KAWELA STREAM BRIDGE

Project Overview

The Central Federal Lands Highway Division of the Federal Highway Administration in cooperation with the Hawaii Department of Transportation is developing a project located on Kamehameha Highway (Route 83) at Mile Post 11.39, the Kawela Stream Bridge, on the Island of Oahu.

A Final Environmental Assessment (EA) and Finding of No Significant Impact (FONSI) has been prepared pursuant to HRS Chapter 343 (as amended), and Hawaii Administrative Rules Title 11, Chapter 200. The document is available for download by clicking on the "All Documents" link on the left side of this page.

Project Details:

Under Construction
Island of Oahu, HI

The project is located on the Kamehameha Highway (Route 83) at mile post 11.39, west of the Kawela Camp Road intersection and Turtle Bay Resort. The project improves the safety and reliability of the existing bridge, through rehabilitation or replacement of the structure, addressing bridge width, load capacity, bridge railing and transitions, and bridge approaches.


Update 10/1/2019

Construction: The construction NTP was issued on February 7, 2019. The contractor has completed initial design submittals and utility relocations are currently underway allowing for on-site work to begin. On-site work began on the Kawela Stream Bridge on September 23, 2019, with clearing and grading activities supporting construction of a temporary by-pass bridge. Work on the by-pass bridge is anticipated to continue into November 2019.


Update 7/1/19

There is no new information to share at this time.


Update 6/1/19

There is no new information at this time.


Update 5/1/2019

Construction: The construction Notice to Proceed was issued on February 7, 2019. The contractor is currently working through design submittals and utility relocation agreements. On-site work is expected to begin in the Summer of 2019.


Update 3/1/19

There is no new information to share at this time.


Update 2/1/2019

Construction: The permanent bridge construction contract was awarded to Kiewit Infrastructure West Co. on September 19, 2018. The construction Notice to Proceed is anticipated to be issued in early February 2019. The contract duration is 274 days beginning from the issuance of Notice to Proceed date. On-site work is expected to begin in the Spring of 2019.


Comments
Construction Amount Between $1,000,000 and $5,000,000

Sections

View a larger interactive map of the project area.

Project Details
Project # HI STP SR83(2)
Project Name KAWELA STREAM BRIDGE
Location Island of Oahu
Status Under Construction

Contact Information

Project Manager: Mike Will
Phone: 720-963-3647
Email: michael.will@dot.gov

Federal Highway Administration
Central Federal Lands Highway Division
12300 West Dakota Avenue
Lakewood, CO 80228
720-963-3500