HI STP SR99(1) KIPAPA STREAM BRIDGE (ROOSEVELT)

Project Overview

The Central Federal Lands Highway Division of the Federal Highway Administration in cooperation with the Hawaii Department of Transportation is developing a project located on the Kamehameha Highway, Route 99, M.P. 14.4, (Kipapa Stream) Roosevelt Bridge, on the Island of Oahu.

Project Details:

In Development
Island of Oahu, HI

The proposed project is located across Kipapa Gulch on Kamehameha Highway (Route 99) at mile post 14.4. The project would improve the safety and reliability of the existing bridge, through rehabilitation, addressing load capacity, bridge railing and transitions.


Update 2/1/18:
Construction Activity Look Ahead

The contractor has finished the Mauka overlay and the finished casting the bridge rail along the Mauka side of the bridge. The contractor is working on finishing installing the underground conduits and pull boxes for the utilities, plus also hanging the conduits across the bridge. The contractor has finished installing the waterline as well.

The contractor will begin demolition of the Makai side overhang to begin construction of the new overhang. The utility companies will move the utility lines over to the Mauka side as well.

Traffic Management

Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 9:00am thru 3:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours
  • Full weekend closures – none are currently planned for the month of February.

Update 1/1/18:
Construction Activity Look Ahead

The contractor will be placing the other half of the mauka overlay. Once that is finished, they will finish forming and placing concrete for the bridge rail on the mauka side of the bridge. They also plan on finishing walls B and C so that the utilities can be moved to the other side of the bridge. The utilities are planned to be placed onto the Makai side of the bridge by the end of the next month

Traffic Management

Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 9:00am thru 3:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours
  • Full weekend closures will be happening 1/12/17.

Update 12/1/17:
Construction Activity Look Ahead

The contractor will be placing the concrete overlay on the mauka side of the bridge and will continue with the utility relocation work. In addition, they will also begin work necessary for temporary utility installations.

Traffic Management

Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 8:00am thru 4:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours
  • Full weekend closures are planned for the weekends of 11/10/17 and 11/17/17.

Update 11/1/17:
Construction Status/description of progress

Construction activities planned to begin/or continue in October include concrete pours for the overhang widening and temporary utility relocations.

Construction Activity Look Ahead

The contractor will be placing the concrete overlay on the mauka side of the bridge and will continue with the utility relocation work. In addition, they will also begin the shoulder widening work necessary for the utility installations.

Traffic Management

Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 8:00am thru 4:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours
  • Full weekend closures are planned for the weekends of 11/10/17 and 11/17/17.

Comments
Construction Amount Between $10,000,000 and $25,000,000

Sections

Map showing general vicinity of project
View a larger interactive map of the project area.

Project Details
Project # HI STP SR99(1)
Project Name KIPAPA STREAM BRIDGE (ROOSEVELT)
Location Island of Oahu
Status Under Construction

Contact Information

Project Manager: Mike Will
Phone: 720-963-3647
Email: michael.will@dot.gov

Federal Highway Administration
Central Federal Lands Highway Division
12300 West Dakota Avenue
Lakewood, CO 80228
720-963-3500