HI STP SR99(1) KIPAPA STREAM BRIDGE (ROOSEVELT)

Project Overview

The Central Federal Lands Highway Division of the Federal Highway Administration in cooperation with the Hawaii Department of Transportation is developing a project located on the Kamehameha Highway, Route 99, M.P. 14.4, (Kipapa Stream) Roosevelt Bridge, on the Island of Oahu.

Project Details:

In Development
Island of Oahu, HI

The proposed project is located across Kipapa Gulch on Kamehameha Highway (Route 99) at mile post 14.4. The project would improve the safety and reliability of the existing bridge, through rehabilitation, addressing load capacity, bridge railing and transitions.


Update 11/1/17:
Construction Status/description of progress

Construction activities planned to begin/or continue in October include concrete pours for the overhang widening and temporary utility relocations.

Construction Activity Look Ahead

The contractor will be placing the concrete overlay on the mauka side of the bridge and will continue with the utility relocation work. In addition, they will also begin the shoulder widening work necessary for the utility installations.

Traffic Management

Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 8:00am thru 4:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours
  • Full weekend closures are planned for the weekends of 11/10/17 and 11/17/17.

Update 10/1/17:

Construction activities planned to begin/or continue in October include concrete pours for the overhang widening and temporary utility relocations.

Full roadway closures are expected on several weekends during the month of October. Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 8:00am thru 4:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours

Please see the following website for current specific closure periods: http://hidot.hawaii.gov/highways/roadwork/

Information on roadway closures will be provided through the above link no later than 2 weeks prior to the closure.


Update 9/1/17:

There is no new information to share at this time.

Construction activities planned to begin/or continue in September include finishing placement of the falsework for the overhang widening and beginning the overhang concrete pour to allow for the necessary cure time prior to placement of the concrete overlay.

Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 8:00am thru 4:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours

Please see the following website for current specific closure periods: http://hidot.hawaii.gov/highways/roadwork/

Information on roadway closures will be provided through the above link no later than 2 weeks prior to the closure.


Update 8/1/17:

Construction activities planned to begin/or continue in August include installation of scaffolding and work platforms to support the future work. Bridge railing removal activities have been initiated are are planned to be completed in August. Removal of the outer portion of the bridge deck is planned to begin in August.

Occasional one lane closures with alternate one-way flagger controlled traffic is anticipated based on the following schedule:

  • Monday thru Friday - Days from 8:00am thru 4:00pm
  • Monday thru Friday - Nights from 6:00pm thru 6:00am
  • Saturdays - 24-hours

Please see the following website for current specific closure periods: http://hidot.hawaii.gov/highways/roadwork/

Information on roadway closures will be provided through the above link no later than 2 weeks prior to the closure.


Comments
Construction Amount Between $10,000,000 and $25,000,000

Sections

Map showing general vicinity of project
View a larger interactive map of the project area.

Project Details
Project # HI STP SR99(1)
Project Name KIPAPA STREAM BRIDGE (ROOSEVELT)
Location Island of Oahu
Status Under Construction

Contact Information

Project Manager

Mike Will
Central Federal Lands Highway Division
Attn: Mike Will
12300 West Dakota Avenue
Lakewood, CO   80228
Phone: 720-963-3647
Fax: 720.963.3596
michael.will@dot.gov