Foothills Parkway Design Build (American Recovery and Reinvestment Act (ARRA) Funds)

Project Description

The project consists of the design and construction of the Foothills Parkway from the western end of the Foothills Parkway near Bridge 8 to the western end of project FOOT 8E17, Bridge 2. The work includes the design and construction of 0.90 mile long new road with walls, five bridges, and other miscellaneous work.

Key Project Dates


Design and Construction: Fall 2010 - Fall 2017

Project Photos

ALTCAPTIONTEXT

Bridge construction is in progress


ALTCAPTIONTEXT

Map showing general vicinity of project
View a larger interactive map of the project area.

Project Details
Project # FOOT 8E14,16,18
Project Name Foothills Parkway Design Build (American Recovery and Reinvestment Act (ARRA) Funds)
Location Blount County, Tennessee
FLMA or Partner(s): Great Smoky Mountains National Park, National Park Service
Status Completed

Contact Information

Project Engineer:Bradley Blevins
Email: Bradley.Blevins@dot.gov

Federal Highway Administration
Eastern Federal Lands Highway Division
21400 Ridgetop Circle
Sterling, Virginia 20166