Middle Fork Snoqualmie River Road
Slope Stablization

Latest Newsletter

Acrobat Icon Newsletter for December 1, 2017  (Acrobat, 939 KB)

Construction Photos

Project Overview

Middle Fork Snoqualmie River Road Construction Project

The Middle Fork Snoqualmie River Road construction project was completed July 10, 2017. This project reconstructed approximately 9.7 miles of the Middle Fork Road, from milepost (MP) 2.7, just past the couplet, to Middle Fork Campground at MP 12.4. The project constructed a 20-foot paved roadway with sections of 18-foot width in constrained locations. This project did not complete a short section of roadway near the river gauging station. This work will be completed on the Middle Fork Snoqualmie River Road Slope Stabilization construction project described below.

Middle Fork Snoqualmie River Road Slope Stabilization Construction Project

The project will reconstruct 400 feet of the Middle Fork Road approximately one mile above the end of the couplet. The project will construct an 18 to 20-foot paved roadway with guardrail, striping, and signing. The project will install draped, pinned, rockfall protection fence on the cut slope needed to widen the roadway. This project will also install riprap under the Lake Dorothy bridge.

Construction will occur from August through October 2017. The project is anticipated to be completed this year.

Location

The Middle Fork Snoqualmie River Road is located north and east of the City of North Bend, which is approximately 30 miles east of Seattle along I-90.

Site Sections

Photo of the Middle Fork Snoqualmie River

Map showing general vicinity of project
View a larger interactive map of the project area.

Project Details
Project # WA PFH 29-1(5)
Project Name Middle Fork Snoqualmie River Road Slope Stabilization
Location Approximately 30 miles east of Seattle, WA along I-90
Status Under Construction
Awarded to S.E.A. Construction LLC
Award Date May 24, 2017
Award Amount $1, 530,170.00
Estimated Completion Fall 2017

Contact Information

Project Email Address:
mfsnoqualmie@dot.gov

Mike Niemi, Project Engineer
Phone: (425) 292-0431
FHWA Project Field Office
8050 Railroad Ave SE Suite C
Snoqualmie, WA 98065

Federal Highway Administration
Western Federal Lands Highway Division
610 East Fifth Street
Vancouver, WA 98661-3801