Develop 50%
ACTIVITY: Develop Intermediate (50%) design consists of the steps below.
- Complete Intermediate Road Safey Evaluation analysis and form.
- Support major structure design
- Develop drainage design
- Develop erosion control design
- Minimize utility conflicts
- Develop temporary traffic control
Step 1 (Weight: 1)
Description: Complete Intermediate Road Safey Evaluation analysis and form.
Step 2 (Weight: 14)
Description: Support major structure design
- Finalize bridge detour alignment for selected alternative
- Provide support to technical services for wall designs (existing cross-sections, wall alignments, etc.)
- Develop wall layout sheets (elevation view)
Step 3 (Weight: 25)
Description: Develop drainage design
- Develop culvert designs and inlet and outlet features adequately to define R/W conflicts and construction easement needs
- Perform/Finalize drainage basin delineations and calculate peak discharges
- Support the major culverts design by Hydraulics
- Update the plan and profile sheets for major drainage structures
Step 4 (Weight: 25)
Description: Develop erosion control design
Develop erosion control plans and identify best management practices
Step 5 (Weight: 10)
Description: Minimize utility conflicts
Revise design to minimize conflicts with utilities
Step 6 (Weight: 25)
Description: Develop temporary traffic control
- Develop preliminary construction phasing plan and/or detour plan
- Determine ROW and/or easement impacts