Utility impacts

ACTIVITY: Verify no additional impacts to utilities consists of the steps below.

  1. Review utility relocation plan
  2. Notify Utilities Technician of outcome

Step 1 (Weight: 50)

Description: Review utility relocation plan

  • Review utility relocation plan against the changes from the PIH field review to ensure that items identified during the PIH field review will not result in changes to the utility relocation plan.
  • (Note: if they do result in changes to the utility relocation plan, the utility company will have to revise the plan, delaying progress on the utility relocation effort.)

Step 2 (Weight: 50)

Description: Notify Utilities Technician of outcome