95% PS&E

ACTIVITY: Prepare and QC Final (95%) PS&E package consists of the steps below.

  1. Finalize Standards, Details, etc.
  2. Finalize Summary of Quantities and Tabulations
  3. Finalize Class A cost estimate
  4. Finalize the Construction schedule (CPM)
  5. Verify mitigation design and support commitments
  6. Finalize Special Contract Requirements (SCR)
  7. Complete 95% QC checklist
  8. Design QC Review
  9. Print and distribute copies of Final (95%) PS&E

Step 1 (Weight: 2)

Description: Finalize Standards, Details, etc.

Verify/update all applicable FLH Standard Plans and WFLHD Details to current version.

Instructions
Resources
References

Step 2 (Weight: 15)

Description: Finalize Summary of Quantities and Tabulations

  • Finalize the plan quantities for all bid items
  • Finalize earthwork quantities and earthwork summary
  • Finalize the bid quantities and Summary of Quantities excel spreadsheet

Step 3 (Weight: 10)

Description: Finalize Class A cost estimate

  • Finalize Class A cost estimate and coordinate with Program Manager.
  • Define pay items and develop unit prices for all work specified in the contract.
  • Verify and document construction price inflation rates and any pay item incentives.

Step 4 (Weight: 10)

Description: Finalize the Construction schedule (CPM)

Instructions
Resources
  • Microsoft Project
  • Construction CFT Member
References

Step 5 (Weight: 10)

Description: Verify mitigation design and support commitments

Instructions
Resources
  • Environment CFT member-Environmental Commitment Summary
  • Environmental Decision Document-CatEx/EA/EIS
  • Permits-special use, SWPP, 404, water, general construction, others
References

Step 6 (Weight: 25)

Description: Finalize Special Contract Requirements (SCR)

  • Verify all applicable SCR's are current and update from the WFL website
  • Incorporate Permit requirements into SCRs
  • Finalize SCR's and finalize format with Office Automation

Step 7 (Weight: 5)

Description: Complete 95% QC checklist

Instructions
Resources

Step 8 (Weight: 20)

Description: Design QC Review

  • Print PS&E for Design QC review.
  • Perform Design QC review.
  • Revise PS&E based on Design QC review

Step 9 (Weight: 3)

Description: Print and distribute copies of Final (95%) PS&E

  • Print hard copy
  • Print to PDF
  • Submit to OA for reproduction
  • Prepare internal and external distribution letter.

Previous  |  Highway Design Process  |  Top  |  Next