70% PS&E
ACTIVITY: Finalize plans, specs, and estimate and QC/assemble PIH (70%) package consists of the steps below.
- Summary of Quantities and Tabulations
- Prepare Class A cost estimate
- Construction Schedule (CPM)
- Provide Environmental Support
- Develop draft Special Contract Requirements (SCR)
- Support/complete permit applications
- Finalize and sign WFLHD-3
- Complete 70% QC checklist
- Design QC Review and revisions
- Print and distribute copies of PIH PS&E
Step 1 (Weight: 20)
Description: Summary of Quantities and Tabulations
- Complete the plan quantities for all bid items
- Complete earthwork quantities and earthwork summary
- Complete tabulation of quantities excel spreadsheet
Instructions
Resources
References
Step 2 (Weight: 10)
Description: Prepare Class A cost estimate
- Prepare Class A cost estimate and coordinate with Program Manager.
- Complete the unit price analysis for all pay items
Step 3 (Weight: 5)
Description: Construction Schedule (CPM)
Step 4 (Weight: 5)
Description: Provide Environmental Support
- Review documents and verify that design incorporates environmental commitments
- Update/Support mitigation design
Step 5 (Weight: 20)
Description: Develop draft Special Contract Requirements (SCR)
Develop draft Special Contract Requirements (SCR) for the 100 - 600 sections
Step 6 (Weight: 5)
Description: Support/complete permit applications
Step 7 (Weight: 5)
Description: Finalize and sign WFLHD-3
Step 8 (Weight: 5)
Description: Complete 70% QC checklist
Step 9 (Weight: 20)
Description: Design QC Review and revisions
- Print PS&E for Design QC review
- Perform Design QC review
- Revise PS&E based on Design QC review
Step 10 (Weight: 5)
Description: Print and distribute copies of PIH PS&E
- Print hard copy
- Print to PDF
- Submit to OA for reproduction
- Prepare internal and external distribution letter.