Develop 30%
ACTIVITY: Develop preliminary (30%) design consists of the steps below.
- Incorporate recommendations
- Layout approach roads.
- Develop pullout and parking area conceptual design.
- Complete Preliminary Road Safety Evaluation
- Identify (location and type) major structures
- Develop preliminary drainage.
- Identify potental site for borrow, staging, waste, etc.
- Determine resource impacts and areas of disturbance
- Identify potential detours and road closures
- Estimate table of quantities for major work items.
Step 1 (Weight: 20)
Description: Incorporate recommendations
Incorporate recommendations from Preliminary Geotech Recommendation Memo and Preliminary Pavement Recommendation Memo.
Instructions
Resources
Step 2 (Weight: 5)
Description: Layout approach roads.
- Layout approach roads: horizontal and vertical alignments for major approaches/intersections
- Plan and profile sheets for major approaches/intersections.
Instructions
Resources
Step 3 (Weight: 10)
Description: Develop pullout and parking area conceptual design.
Instructions
Resources
Step 4 (Weight: 1)
Description: Complete Preliminary Road Safety Evaluation
Complete Preliminary Road Safety Evaluation analysis and form.
Instructions
Resources
Step 5 (Weight: 10)
Description: Identify (location and type) major structures
Identify (location and type) major structures on plan and profile sheets.
Step 6 (Weight: 10)
Description: Develop preliminary drainage.
Develop preliminary drainage for major and minor drainage locations and approximate quantities
Instructions
Resources
Step 7 (Weight: 5)
Description: Identify potental site for borrow, staging, waste, etc.
Identify potential disposal sites, borrow areas, staging areas, and water sources.
Step 8 (Weight: 10)
Description: Determine resource impacts and areas of disturbance
Step 9 (Weight: 15)
Description: Identify potential detours and road closures
Identify potential detours and road closures and evalute possible construction phasing
Instructions
Resources
Step 10 (Weight: 14)
Description: Estimate table of quantities for major work items.. Estimate table of quantities for major work items:
- earthwork quantities,
- potential waste and borrow quantities